Geothermal

Edsel & Eleanor Ford House

Administration Building & Visitor Center

Administration Building Project: 20,000 GSF
Visitor Center Project: 40,000 GSF
Total Project: 60,000 GSF
Construction Total: $35.5 Million

Extensive project included:

  • Food service areas, storage, preparation, and cooking spaces
  • Civil, Architectural, Structural, & MEP changes and upgrades
  • Parking Lot & Existing building improvements

New Visitor Center:

  • Replace Existing visitor Center
  • 2-Story
  • Retail Area, Food Service, Exhibits, Classrooms, & Event Space

New Administration Building include:

  • 2-Story
  • Offices, Meeting Rooms, Boardroom, Social Space, Exercise Space, & Kitchen
  • Solar Panels, Geothermal, & Sustainable Energy
  • LEED Gold Rating

Geo-exchange field:

  • 15 Closed loop bores. 350’-400’ deep

University of Michigan Hayward Street Geothermal

Ann Arbor, MI

Project: 100 Bores, 3,320 GSF CEP

Geo-exchange field:

  • 100 Closed loop bores. 700’ deep
  • Heat Pumps 390 Ton
  • Vertical Bores
  • Underground closed loop

Geothermal Field

New Construction

Project: 880 Bores, 12,800 GSF CEP

Geo-exchange field:

  • 880 Closed loop bores. 1,000’ deep
  • Heat Pumps 2,000 Ton
  • Heat Recovery Chillers
  • Vertical Bores
  • Inclined Bores 5 degrees & 10 degrees